Bespoke protective case moulds: when a new mould is justified, what information is needed, the 125-day programme and the economics of tooling.

Start Your OEM Project→ Find your case
Overview

A new mould buys a distinctive shape, an exact external footprint or a structural feature no stock shell has. It also buys four months of lead time and a capital cost, so it has to be justified.

01

Confirm the geometry cannot be met by a stock shell with usable clearance

02

Freeze the equipment envelope, the stacking requirement and the hardware positions

03

Mould design and flow analysis; gate, cooling and parting-line review with the customer

04

Mould machining, normally inside the 125-day programme

05

Trial shots, dimensional sign-off against the drawing, then production release

When a mould makes sense

Above roughly 3,000 units per year of one geometry, a mould usually pays for itself against the cost of accepting a compromise shell. Below that, we will show you the closest stock model instead.

FAQ

Before you commit

Who owns the mould?

Ownership is agreed in the tooling contract before cutting starts. Where the customer funds the tool, the mould is held for that customer production and is not used for third parties.

What is the lead time?

One hundred and twenty-five days from confirmed drawing and deposit when a new mould is required.